Property Owner's Perspective
If you agree to have a contractor do work
on your home (remodeling, new
construction, additions, etc.), you need to
protect your rights upfront. Do not pay the
entire contract price upfront. Rather, you
should agree to pay in installments and
make sure the subcontractors (if any) will
get paid. Otherwise, the subcontractors
may get a lien against your property.
Conversely, if you are the subcontractor,
you need to protect your rights upfront,
also.

Call us ASAP.
You will find great benefit in contacting an
attorney before you agree to any major
construction or improvement of your home
or business. An attorney can help you put
your money in escrow and/or negotiate an
installment plan such that you are not
paying the contractor the entire balance
upfront. Give is a call and we'll tell you just
how affordable it can be.

Mechanic's
Lien Law
all rights reserved Todd W. Elliott 2008
Email Questions: FreeCaseEvaluation

2007 AMENDMENTS TO THE LAW
The 1963 statute in this area existed with only minor changes until 2007. Contact our
lawyers to find out how the 2007 amendments changed the following statute:

Unconsolidated Pennsylvania Statutes
MECHANICS' LIENS (TITLE 49)
MECHANICS' LIEN LAW OF 1963
ARTICLE I. SHORT TITLE
§ 1101. Short title.
This act shall be known and may be cited as the "Mechanics' Lien Law of 1963 ".

ARTICLE II. DEFINITIONS
§ 1201. Definitions.
The following words, terms and phrases when used in this act shall have the meaning ascribed to them in
this section, except where the context clearly indicates a different meaning:


1. "Improvement"
includes any building, structure or other improvement of whatsoever kind or character erected or constructed
on land, together with the fixtures and other personal property used in fitting up and equipping the same for
the purpose for which it is intended.
2. "Property"
means the improvement the land covered thereby and the lot or curtilage appurtenant thereto belonging to the
same legal or equitable owner reasonably needed for the general purposes thereof and forming a part of a
single business or residential plant.
3. "Owner"
means an owner in fee, a tenant for life or years or one having any other estate in or title to property.
4. "Contractor"
means one who, by contract with the owner, express or implied, erects, constructs, alters or repairs an
improvement or any part thereof or furnishes labor, skill or superintendence thereto; or supplies or hauls
materials, fixtures, machinery or equipment reasonably necessary for and actually used therein; or any or all
of the foregoing, whether as superintendent, builder or materialman. The term also includes an architect or
engineer who, by contract with the owner, express or implied, in addition to the preparation of drawings,
specifications and contract documents also superintends or supervises any such erection, construction,
alteration or repair.
5. "Subcontractor"
means one who, by contract with the contractor, express or implied, erects, constructs, alters or repairs an
improvement or any part thereof; or furnishes labor, skill or superintendence thereto; or supplies or hauls
materials, fixtures, machinery or equipment reasonably necessary for and actually used therein; or any or all
of the foregoing, whether as superintendent, builder or materialman. The term does not include an architect or
engineer who contracts with a contractor or subcontractor, or a person who contracts with a subcontractor
or with a materialman.
6. "Claimant"
means a contractor or subcontractor who has filed or may file a claim under this act for a lien against
property.
7. "Materials"
means building materials and supplies of all kinds, and also includes fixtures, machinery and equipment
reasonably necessary to and incorporated into the improvement.
8. "Completion of the work"
means performance of the last of the labor or delivery of the last of the materials required by the terms of the
claimant's contract or agreement, whichever last occurs.
9. "Labor"
includes the furnishing of skill or superintendence.
10. "Erection and construction"
means the erection and construction of a new improvement or of a substantial addition to an existing
improvement or any adaptation of an existing improvement rendering the same fit for a new or distinct use
and effecting a material change in the interior or exterior thereof.
11. "Alteration and repair"
means any alteration or repair of an existing improvement which does not constitute erection or construction
as defined herein.
12. "Erection, construction, alteration or repair"
includes
(a) Demolition, removal of improvements, excavation, grading, filling, paving and landscaping, when such
work is incidental to the erection, construction, alteration or repair;
(b) Initial fitting up and equipping of the improvement with fixtures, machinery and equipment suitable to the
purposes for which the erection, construction, alteration or repair was intended; and
(c) Furnishing, excavating for, laying, relaying, stringing and restringing rails, ties, pipes, poles and wires,
whether on the property improved or upon other property, in order to supply services to the improvement.
13. "Prothonotary"
means the prothonotary of the court or courts of common pleas of the county or counties in which the
improvement is situate.

ARTICLE III. RIGHT TO LIEN
§ 1301. Right to lien; amount.
§ 1302. Presumption as to use of materials.
§ 1303. Lien not allowed in certain cases.
§ 1304. Excessive curtilage.
§ 1305. Right to lien in case of noncompletion of work.
§ 1306. Consolidation or apportionment of claims.
§ 1307. Removal or detachment of improvement subject to claim.

§ 1301. Right to lien; amount.
Every improvement and the estate or title of the owner in the property shall be subject to a lien, to be
perfected as herein provided, for the payment of all debts due by the owner to the contractor or by the
contractor to any of his subcontractors for labor or materials furnished in the erection or construction, or the
alteration or repair of the improvement, provided that the amount of the claim, other than amounts determined
by apportionment under section 306(b) of this act, shall exceed five hundred dollars ($500).

§ 1302. Presumption as to use of materials.
Materials for use in or upon an improvement placed on or near the property or delivered to the owner
pursuant to a contract shall be presumed to have been used therein in the absence of proof to the contrary.

§ 1303. Lien not allowed in certain cases.
(a) Persons Other Than Contractors or Subcontractors. No lien shall be allowed in favor of any person other
than a contractor or subcontractor, as defined herein, even though such person furnishes labor or materials
to an improvement.

(b) Public Purpose. No lien shall be allowed for labor or materials furnished for a purely public purpose.

(c) Conveyance Prior to Lien. If the property be conveyed in good faith and for a valuable consideration prior
to the filing of a claim for alterations or repairs, the lien shall be wholly lost.

(d) Leasehold Premises. No lien shall be allowed against the estate of an owner in fee by reason of any
consent given by such owner to a tenant to improve the leased premises unless it shall appear in writing
signed by such owner that the erection, construction, alteration or repair was in fact for the immediate use
and benefit of the owner.

(e) Security Interests. No lien shall be allowed for that portion of a debt representing the contract price of any
materials against which the claimant holds or has claimed a security interest under the Pennsylvania Uniform
Commercial Code or to which he has reserved title or the right to reacquire title.

§ 1304. Excessive curtilage.
Where an owner objects that a lien has been claimed against more property than should justly be included
therein, the court upon petition may, after hearing by deposition or otherwise, limit the boundaries of the
property subject to the lien. Failure to raise this objection preliminarily shall not be a waiver of the right to plead
the same as a defense thereafter.

§ 1305. Right to lien in case of noncompletion of work.
Except in case of destruction by fire or other casualty, where, through no fault of the claimant, the
improvement is not completed, the right to lien shall nevertheless exist.

§ 1306. Consolidation or apportionment of claims.
(a) Consolidation of Claims. Where a debt is incurred for labor or materials furnished continuously by the
same claimant for work upon a single improvement but under more than one contract, the claimant may elect
to file a single claim for the entire debt. In such case, "completion of the work" shall not be deemed to occur
with respect to any of the contracts until it has occurred with respect to all of them.

(b) Apportionment of Claims. Where a debt is incurred for labor or materials furnished by the same claimant
for work upon several different improvements which do not form all or part of a single business or residential
plant, the claimant shall file separate claims with respect to each such improvement, with the amount of each
claim determined by apportionment of the total debt to the several improvements, and in such case, the
amount of each separate claim may be less than five hundred dollars ($500), provided that the total debt
exceeds five hundred dollars ($500). In no other case shall an apportioned claim be allowed.

§ 1307. Removal or detachment of improvement subject to claim.
(a) Removal Prohibited; Effect.-No improvement subject to the lien of a claim filed in accordance with this act
shall be removed or detached from the land except pursuant to title obtained at a judicial sale or by one
owning the land and not named as a defendant. Any improvement otherwise removed shall remain liable to
the claim filed, except in the hands of a purchaser for value.

(b) Restraint of Removal by Court.-The court may on petition restrain the removal of the improvement in
accordance with the Pennsylvania Rules of Civil Procedure governing actions to prevent waste.

ARTICLE IV. WAIVER OF LIEN; EFFECT OF FILING
§ 1401. Waiver of lien by claimant.
A contractor or subcontractor may waive his right to file a claim by a written instrument signed by him or by
any conduct which operates equitably to estop such contractor or subcontractor from filing a claim.

§ 1402. Waiver by contractor; effect on subcontractor.
A written contract between the owner and contractor or a separate written instrument signed by the
contractor, which provides that no claim shall be filed by anyone, shall be binding; but the only admissible
evidence thereof, as against a subcontractor, shall be proof of actual notice thereof to him before any labor
or materials were furnished by him; or proof that such contract or separate written instrument was filed in the
office of the prothonotary prior to the commencement of the work upon the ground or within ten (10) days
after the execution of the principal contract or not less than ten (10) days prior to the contract with the
claimant subcontractor, indexed in the name of the contractor as defendant and the owner as plaintiff and
also in the name of the contractor as plaintiff and the owner as defendant. The only admissible evidence that
such a provision has, notwithstanding its filing, been waived in favor of any subcontractor shall be a written
agreement to that effect signed by all those who, under the contract, have an adverse interest to the
subcontractor's allegation.

§ 1403. Release as waiver.
A release signed by the claimant shall not operate as a waiver of the right to file a claim for labor or materials
subsequently furnished, unless it shall appear thereby that such was the express intent of the party.

§ 1404. Effect of credit or collateral.
The giving of credit or the receipt of evidence of indebtedness or collateral otherwise than as provided in
section 303(e) shall not operate to waive the right to file a claim, but where credit is given, no voluntary
proceedings shall be taken by the claimant to enforce the lien until the credit period has expired.

§ 1405. Right of owner to limit claims to unpaid balance of contract price.
Where there has been no waiver of liens and the claims of subcontractors exceed in the aggregate the
unpaid balance of the contract price specified in the contract between the owner and the contractor, then if
the subcontractor has actual notice of the total amount of said contract price and of its provisions for the time
or times for payment thereof before any labor or materials were furnished by him, or if such contract or the
pertinent provisions thereof were filed in the office of the prothonotary in the time and manner provided in
section 402, each claim shall, upon application of the owner, be limited to its pro-rata share of the contract
price remaining unpaid, or which should have remained unpaid, whichever is greatest in amount at the time
notice of intention to file a claim was first given to the owner, such notice inuring to the benefit of all
claimants.

§ 1406. Right of subcontractor to rescind after notice of contract provisions.
Any provisions of a contract between the owner and the contractor, which reduce or impair the rights and
remedies of a subcontractor or which postpone the time for payment by the owner to the contractor for a
period exceeding four (4) months after completion of the work, shall be grounds for recision by the
subcontractor of his contract with the contractor, unless such subcontractor was given actual notice thereof
prior to the time of the making of his contract with the contractor, or the contract or the pertinent provisions
thereof were filed in the office of the prothonotary in the time and manner provided by section 402. Such
recision shall not impair the right of the subcontractor to recover by lien or otherwise for work completed prior
thereto.

§ 1407. Contracts not made in good faith; effect.
A contract for the improvement made by the owner with one not intended in good faith to be a contractor shall
have no legal effect except as between the parties thereto, even though written, signed and filed as provided
herein, but such contractor, as to third parties, shall be treated as the agent of the owner.

ARTICLE V. FILING AND PERFECTING CLAIM; DISCHARGE OF LIEN
§ 1501. Notice by subcontractor as condition precedent.
§ 1502. Filing and notice of filing of claim.
§ 1503. Contents of claim.
§ 1504. Amendment of claim.
§ 1505. Procedure for contesting claim; preliminary objections.
§ 1506. Rule to file claim.
§ 1507. Indexing claims, et cetera.
§ 1508. Priority of lien.
§ 1509. Effect of forfeiture of leasehold.
§ 1510. Discharge of lien on payment into court or entry of security.

§ 1501. Notice by subcontractor as condition precedent.
(a) Preliminary Notice in Case of Alteration and Repair. No claim by a subcontractor for alterations or repairs
shall be valid unless, in addition to the formal notice required by subsection (b) of this section, he shall have
given to the owner, on or before the date of completion of his work, a written preliminary notice of his
intention to file a claim if the amount due or to become due is not paid. The notice need set forth only the name
of the subcontractor, the contractor, a general description of the property against which the claim is to be
filed, the amount then due or to become due, and a statement of intention to file a claim therefor.

(b) Formal Notice in All Cases by Subcontractor. No claim by a subcontractor, whether for erection or
construction or for alterations or repairs, shall be valid unless, at least thirty (30) days before the same is
filed, he shall have given to the owner a formal written notice of his intention to file a claim, except that such
notice shall not be required where the claim is filed pursuant to a rule to do so as provided by section 506.

of service, shall be filed within twenty (20) days after service setting forth the date and manner of service.
Failure to serve such notice or to file the affidavit or acceptance of service within the times specified shall be
sufficient ground for striking off the claim.

(b) Venue; Property in More Than One County. Where the improvement is located in more than one county, the
claim may be filed in any one county, the claim may be filed in any one or more of said counties, but shall be
effective only as to the part of the property in the county in which it has been filed.
the amount or sum claimed to be due; and
such description of the improvement and of the property claimed to be subject to the lien as may be
reasonably necessary to identify them.
ame as a defense in subsequent proceedings.

§ 1508. Priority of lien.
The lien of a claim filed under this act shall take effect and have priority:

(a) In the case of the erection or construction of an improvement, as of the date of the visible commencement
upon the ground of the work of erecting or constructing the improvement; and

(b) In the case of the alteration or repair of an improvement, as of the date of the filing of the claim.

§ 1509. Effect of forfeiture of leasehold.
The lien of every claim shall bind only the interest of the party named as owner of the property at the time of
the contract or acquired subsequently by him, but no forfeiture or surrender of a leasehold, or tenancy,
whether before or after the filing of the claim, shall operate to prejudice its lien against the fixtures, machinery
or other similar property.

§ 1510. Discharge of lien on payment into court or entry of security.
(a) Cash Deposit. Any claim filed hereunder shall, upon petition of the owner or any party in
interest, be discharged as a lien against the property whenever a sum equal to the amount
of the claim shall have been deposited with the court in said proceedings for application to
the payment of the amount finally determined to be due.

(b) Pro-rata Allocation. In any case where the claim or claims are limited in the manner and
to the extent provided in section 405, the owner may deposit with the court in separate
proceedings a sum equal to the total allowable amount of said claims determined in
accordance with said section, whereupon the court, on petition of such owner, shall order all
of said claims discharged as liens against the property, and the sum so deposited applied
pro rata to the payment thereof in the amounts finally determined to be due.

(c) Refund of Excess. Any excess of funds paid into court as aforesaid, over the amount of
the claim or claims determined and paid therefrom, shall be refunded to the owner or party
depositing same upon application for the same.

(d) Security in Lieu of Cash. In lieu of the deposit of any such sum or sums, approved
security may be entered in such proceedings in double the amount of the required deposit,
or in such lesser amount as the court shall approve, which, however, shall in no event be
less than the full amount of such required deposit; and the entry of such security shall
entitle the owner to have such liens discharged to the same effect as though the required
sums had been deposited in court as aforesaid.

(e) Authority of Court. The court, upon petition filed by any party, and after notice and
hearing, may upon cause shown:


require the increase or decrease of any deposit or security;
strike off security improperly filed;
permit the substitution of security and enter an exoneration of security already given.

(d) Limitation on Time of Obtaining Judgment. A verdict must be recovered or judgment
entered within five (5) years from the date of filing of the claim. Final judgment must be
entered on a verdict within five (5) years. If a claim is not prosecuted to verdict or judgment,
as provided above, the claim shall be wholly lost: Provided, however, That in either case, if a
complaint has been or shall be filed in the cause and if the cause has been or shall be at
issue, all time theretofore or thereafter consumed in the presentation and disposition of all
motions and petitions of defendants, substituted defendants and intervenors in the cause,
and in any appeal or appeals from any order in the cause, from the date of perfection of
such appeal to the date of return of the certiorari from the appellate court to the court of
common pleas, shall be excluded in the computation of the five (5) year period herein
provided.